July 01 2023

Phase 1 - CORE ASSETS

Core Assets include the water network, wastewater network, storm water network, road network and bridges and culverts.

  • Document and review core asset inventory.
  • Document existing levels of service for core assets
  • Complete lifecycle analysis and assess risk/criticality of each core asset to inform future desired levels of service.
  • Determine estimated replacement and operational cost. 
July 01 2024

Phase 2 - ALL OTHER CORPORATE ASSETS

Include non-core assets into the Asset Management Plant.  This includes buildings, fleet, machinery and equipment and furniture and fixtures.  

  • Review and make any required adjustments or updates to the core asset inventory
  • Update asset inventory to include all assets owned by the Town of Cochrane as defined in the Strategic Asset Management Policy
  • Document existing levels or service for all other assets 
  • Determine replacement cost and operating cost. 
July 01 2025

Phase 3 - FINANCING, AND ESTABLISH LEVEL OF SERVICE

Phase 3 is building on Phase 1 and 2 by adding Proposed Level of service and lifecycle management and financial strategy. 

  • Review and make any required adjustments or updates to the asset management plan. 
  • Develop proposed technical and community levels of service 
  • Update asset lifecycles and risk models 
  • Identify financial strategies to deliver proposed levels of service and address funding shortfalls.